Caring about Carling Last night was the first Public Advisory Committee (PAC) meeting for the Carling Avenue reconstruction project from the O-Train to Bronson Avenue. Scheduled for 2011, its for a complete rebuild of the street: new sewers, water mains, dozens of cable and gas pipes, curbs, sidewalks, lighting...everything. The handout emphasized the following priorities in this order: pedestrian, cycling, transit, vehicle. Of course, the the Technical Adisory Committee (TAC) had first whack at the project and they specified two through lanes in each direction, a bus lane, a cycling lane,very generous turn lanes, etc etc all of which exceeds the available right of way. Now, which elements do we guess might get dropped? No points for the correct answer: car lanes, bus lane, bike lane if room, "2m sidewalk (where feasible)". So much for ped priority. And for streetscaping ... to be added in at the end on the leftover spaces. So, I spent the evening in plesant dialogue w...